SUMMARY OF ITB

For a copy of the document in its entirity, call 561-493-2550 or email your request.

SCOPE OF WORK:

The Lake Worth Beach CRA, has an existing immediate need for the complete demolition of structures, asphalt (unless otherwise noted), concrete, vegetation, trees (unless otherwise noted), underground amenities and site improvements (to include removal of concrete slabs and foundations on properties as applicable), for the property listed under the Site Information portion of this Invitation for Bids.

MINOR Asbestos abatement is required where the associated asbestos survey shows the existence of asbestos. Asbestos Abatement shall include proper removal, transportation and disposal, with a post-job write-up reflecting these actions. Additionally, Lead Surveys have been performed, indicating whether lead was found to be present or not, and if so, whether it was above or below the regulatory levels. The presence of lead in construction debris has the potential to impose limitation on where and how the debris may be disposed. Please perform a Toxicity Characteristic Leaching Procedure (TCLP) for lead, to determine the amount of leachable lead present, and keep the results of the TCLP on hand for Agency review. It is the responsibility of the demolition company to be responsible for all required abatement and disposal necessary, of asbestos and lead-based materials. Unless otherwise indicated, all asbestos and lead surveys are available for viewing at the CRA office or can be emailed upon request.

The selected Demolition Contractor must insure each of the requirements listed below, is accomplished on the property, and the cost is to be included in the quote/bid. If any of the requirements are unclear, do not assume the answer, please inquire with the CRA and receive a written response.

1. Secure the abatement permits (when applicable) and the demolition and lot clearing permits from the City of Lake Worth Beach and pay the associated permit fees. The selected contractor is responsible for obtaining all releases from the City of Lake Worth Beach.

2. Secure the following releases from the City of Lake Worth Beach: a. Utility releases (Water, Sewer, Electric) b. Gas release from FPU c. Planning and Zoning d. Public Services (silt fence and landscaping)

3. Schedule a pre-demolition site meeting with the CRA, who will insure the Building Department, Public Services Department are present if necessary.

4. Insure that a properly-installed silt fence is erected around the project site.

5. Insure the City knows the property is owned by the Lake Worth Beach CRA when/if requesting hydrant water meters.

6. Provide or otherwise contract to provide any asbestos and/or lead abatement which is required. (Asbestos and lead surveys have been performed on all properties which are subject to this Invitation for Bids. The results are located at the CRA’s office. Copies of the reports can be emailed to bidders. The cost of abatement must be part of your quote/bid.

7. Hydrant Water Meters are available from the City of Lake Worth Beach, if necessary

8. Provide a rodent free certification for both properties

9. A ten (10) day notice must be filed with the Palm Beach County Health Department prior to asbestos removal and demo of structures. This fee must be included in your bid price.

10. Demolish structures and improvements on the property, to include all vegetation (unless otherwise noted), trees, laundry lines, posts, fences (unless otherwise noted), below-grade footings, below-grade utility pipes, lines, asphalt, concrete, and conduit. Lot Clearing will be required, although designated trees may be requested to be preserved by the City of Lake Worth Beach during the permitting process or at the pre-demolition meeting.

11. Provide dust control during asbestos removal and structural demolition and ensure silt fences are installed at all locations.

12. After demolition is complete, proper grading of the site is required to support lot sodding, so that City of Lake Worth Beach inspectors are satisfied.

13. Install bahia sod to areas in which structures and concrete were demolished only.

14. Clean the public right of way upon completion of the work

15. Repair any and all damage to the sidewalks, curbs and city streets/alleys that resulted from the demolition activity (pre-existing conditions will be noted)

16. Remove the silt fence upon completion and as a requirement of permit closure.

17. Schedule a post-demolition inspection with the CRA to insure compliance with the contract requirements.

18. Failure to meet the milestone dates could result in violation of this agreement

 

For a copy of the document in its entirity, call 561-493-2550 or email your request.